BusinessContracts and ProcurementNNPC signs $1.5b contract for repairs of Port Harcourt refinery

NNPC signs $1.5b contract for repairs of Port Harcourt refinery

Date:

Share post:

- Advertisement -

By Edith Ike-Eboh

The Nigerian National Petroleum Corporation (NNPC) will award contracts for the rehabilitation of Kaduna and Warri refineries at the end of June.

The Group Managing Director, NNPC, Malam Mele Kyari, made this known today in Abuja at the signing of the $1.5 billion contract for the rehabilitation of the Port Harcourt Refinery Company (PHRC).

He said the process of selection of contractors for Kaduna and Warri was ongoing.

- Advertisement -

Today’s signing was with Maire Tecnimont SPA, an Italian Company.

He said the contractor was selected with high level of transparency.

Maire Tecnimont S.p.A. is an Italian group comprising 50 companies in the engineering, technology and energy sectors.

It deals in plant engineering in oil and gas, chemicals and petrochemicals, in green chemistry and in technology supporting energy transition.

“My Colleagues and I are very proud of what is happening today, a tender process which cumulated in this event of today, the signing of contract for the rehabilitation of Port Harcourt Refinery.

“This is a monumental history for us,” Kyari said.

He said the corporation was aware of misgiving in the public on the cost of rehabilitation of the refinery but noted that the NNPC would maintain high level of transparency in the process of carrying out the work.

- Advertisement -

He said government had admitted the fact it made a lot of mistakes with the Turnaround Maintenance (TAM) of the refineries over the years.

He explained that NNPC selected the contractor through transparent Engineering, Procurement and Construction (EPC) process and also by the recommendation of the original builders of the refinery.

“We have decided to pick up our pieces and follow the EPC contract process. This is probably the most transparent EPC that anyone can put on the table.

“This is because we even involved those that ought not to be in the process for transparency sake.

- Advertisement -

“This moment, we are happy to deliver on this, happy that Mr President will be able to meet his promises to Nigerians,” he said.

Commenting on the cost, Kyari said the 1.5 billion dollars earlier reported in the media was the actual cost of the work inclusive of Value Added tax (VAT).

“For avoidance of doubts, the figure you see in the media included VAT, we have disclosed everything that it will cost in the rehabilitation of the refinery.

“Actual cost exclusive of VAT is 1.299 billion dollars with provisional sum of 162 billion dollars.

“That is the value of the contract. What you see in the Media is around 1.5 billion dollars because we are a very compliant company, we included everything that is needed that people should know. We are also proud of this,’’ he said.

The GMD further noted that the rehabilitation would involve replacement, upgrade and change of obsolete parts of the refinery.

He said the books of NNPC would be open for any public audit during and after the work was completed.

He commended all stakeholders for the support and assured that the project would be delivered at the agreed cost and time.

He charged the contractor to be mindful of the fact that the project was a national project and should hand over any person that perpetuates any fraudulent act to the government.

The Managing Director of the PHRC, Ahmed Dikko, commended the NNPC for its effort in ensuring that the contract was signed.

He said the development was a dream come true, and the result of conscious efforts and dedication of the federal government and NNPC.

He said the scope of the business for the selected contractor was engineering, procurement, construction and installation of works of the rehabilitation of the Refinery.

“The lump sum price of this contract is 1,397 billion dollars which included VAT. The provision sum approved is 162,239 million dollars.

“The mode of payment for the contract will be through an escrow account which will be established within the next two months maximum.

“The commencement period of this programme is today after the signing,” he said.

He added that the maximum time of completion of the project would be 44 months, but the phase one would finish within 24 months while phase 2, 32 months and last phase 44 months.

The Managing Director of Maire Tecnimont SpA, Davide Pelizzola, said the contract would deepen the relationship between the company and Nigeria.

He assured that it would be committed to ensure that the rehabilitation project would be completed at the estimated time.

- Advertisement -

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Related articles

Port Harcourt refinery, tanker drivers at war over delay in product loading

BBy Victor AhiumaYoung & Davies IheamnachorThe Port Harcourt Refining Company, PHRC, and Petroleum Tanker Drivers, PTD, are at...

Port Harcourt refinery yet to begin bulk sales, pricing under review – NNPC

The Port Harcourt Refining  has not started bulk sales of petroleum products or opened its purchase portal as...

Uganda to Fund $4-Billion Oil Refinery after Ditching Efforts to Tap Markets

By Charles KennedyThe government of African country Uganda plans to wholly finance a $4-billion oil refinery through equity,...

How we brought Port Harcourt Refinery back to life — NNPCL spokesperson

In this interview, Olufemi Soneye, Chief Corporate Communications Officer of the Nigeria National Petroleum Corporation Limited (NNPCL), clears...

Unforeseen challenges delaying Lagos-Ibadan rail project – Rotimi Amaechi

The Minister of Transportation, Rotimi Amaechi, unforeseen challenges are affecting the construction of a standard gauge railway line...

Why many countries are rejecting Nigerian exports — Foreign Minister

The Minister of Foreign Affairs, Mr Geoffrey Onyeama on Saturday lamented the rejection of Nigerian exports by other...

Buhari Commissions 2.0MW Solar Powered electrification project In Sokoto

By Musa Ubandawaki SokotoPresident Muhammadu Buhari yesterday Monday commissioned 2.0 megawatts solar powered Electrification project in Usmanu Danfodio...

Manufacturing, the FX Situation and the Nigerian Economy Abdulsamad Rabiu

The Nigerian Dream, if there ever were such a notion, is facing its greatest challenge in recent times....